In 2026, Sound Transit rewrote West Seattle light rail in two ways that matter to anyone buying a house in Genesee. It dropped the station planned at the neighborhood's southeast edge, and it moved the opening date to 2035. A home bought this winter will be owned through about eight years of construction before the first train runs, and the only station on this part of the peninsula will be at 41st and Alaska. So the useful question for a Genesee buyer has changed. Asking how close a house sits to "the light rail" matters less now than asking which years of the project you expect to own it.
In October 2024 the Sound Transit Board chose the route West Seattle had been debating for years. Alaska Junction Station would sit in a tunnel under 41st Avenue SW and SW Alaska Street, with entrances on both sides of Alaska. Avalon Station would sit in a lidded trench under 35th Avenue SW, just south of SW Genesee Street. For Genesee, that meant a station near each edge of the neighborhood: one a few blocks north at the Junction and one at its southeast corner.
The second decision came on May 28, 2026, when the Board approved an updated ST3 System Plan. Sound Transit's project site calls removing Avalon Station "the most significant change" to the project. The line will now have three new stations, at SODO, Delridge and Alaska Junction, and Sound Transit says losing Avalon puts more of the route in a tunnel and means fewer properties have to be acquired. Those refinements still have to be confirmed with the Federal Transit Administration.
The cuts were first presented to a Board committee in March. West Seattle Blog's live account of that meeting reports that the tunnel portal moves to the east side of Avalon and that the Junction station gets shallower, about 30 feet down instead of 60, because the tail track beyond the station is eliminated. Project staff told the committee that Avalon was expected to have low ridership, that about half its riders would have come by bus, and that those bus routes would continue.
The east side of Genesee was once mapped around a station of its own. It is now in bus territory, a longer walk from a single stop at the Junction.
Sound Transit posted the schedule change on August 13, 2026. After reviewing the timeline, the agency set 2035 as the new start of service. It gave two reasons: cost-savings work that held up final design and property acquisition until an affordable system plan existed, and a closer look at the new light-rail-only bridge over the Duwamish River, which needs more construction time. Sound Transit says these add about two to three years and that an independent third party checked the schedule.
| Period | What Sound Transit has scheduled |
|---|---|
| June 2026 | Board authorized final design contracts |
| August and October 2026 | Board authorized the first two property acquisition packages |
| Winter 2026–27 | Construction management services come on board |
| 2027 | Major construction contracts awarded for the bridge, tunnel, guideways and stations |
| 2027 to 2035 | Construction |
| 2035 | Service begins |
The table draws on Sound Transit's August update, its milestone page and the two fall Board resolutions. The agency also reports more than $2 billion in cost savings across the project. According to The Urbanist, most of that comes from dropping Avalon.
Seen from a house in Genesee, the calendar has three parts. Through 2026 and into 2027 the project is mostly paperwork, appraisals and design. From 2027 until the mid-2030s it is a construction project a few blocks north. Only in 2035 does it become what people picture when they say "near the light rail."
Most buyers will first see the project's footprint in two Board resolutions passed this fall.
On August 27, 2026, the Board authorized acquiring all or part of 55 parcels. Forty-three are full acquisitions that require relocation and 12 are partial. The parcel list includes 4000, 4001 and 4022 SW Alaska Street and several addresses on 40th and 41st Avenue SW near the Junction station.
On October 22, 2026, a second resolution covered 64 more parcels. Three are full acquisitions, one is a partial industrial acquisition, and the other 60 are easements. The October package requires one residential relocation and one nonresidential relocation. The list includes City View West at 3000 SW Avalon Way.
The footprint has shrunk overall. In March 2026, as West Seattle Blog reported, Sound Transit estimated the revised plan would displace about 100 properties, roughly a third of an earlier estimate that counted 160 residences and 130 businesses. The smaller Junction station keeps Jefferson Square out of the footprint, which Westside Seattle also reported from Sound Transit's April briefing to the West Seattle Chamber.
The station entrance is planned for the northeast corner of Alaska and 41st, steps from Sound and Fog, where neighborhood advocates began a walking tour of the station area on October 28, 2026. West Seattle Blog quoted Deb Barker of the Morgan Community Association on what participants learned. Intersections along Alaska will become four-way stops. Traffic will still be able to cross Alaska north and south on 40th, 41st and 42nd. Drop-offs by car will happen on 41st, next to the station. SDOT will look at whether stop signs and more traffic calming are needed on Oregon.
For Genesee, those cross streets matter. Forty-first and 42nd run from the neighborhood's northern blocks toward the station entrance.
The City of Seattle is running its own plan for the area around the station, a Transit-Oriented Community Action Plan that covers about a half-mile walk from the entrance. The city held community engagement in Spring 2026, expects a draft plan in Spring 2027, and plans to start implementation in 2027. Nothing in the plan has been adopted yet, so for now it is something to watch.
Taken together, the project shows up differently depending on how long a buyer plans to stay.
A buyer who expects to sell within about five years will own through the start of construction and sell in the middle of it. For that buyer, the parts that will matter are the cross streets, the four-way stops on Alaska and how the blocks north of Charlestown work while a station is built under 41st. A finished station will not be part of that ownership.
A buyer who plans to stay past 2035 gets the full timeline: the construction years and then a tunnel station a short walk from Genesee's northern blocks. For that buyer, how far a house is from the northeast corner of 41st and Alaska is a real factor in comparing streets. It is a 2035 factor, though, and the 2026 price is set by buyers working on every one of these timelines.
The southeast blocks near 35th and Genesee now look different from how they looked two years ago. These houses were once near the planned Avalon station. The current plan has no station there, and Sound Transit has said buses will keep serving those riders. A house on those blocks is now close to the tunnel route and the Avalon-side portal, and farther from a stop than it was on the 2024 map.
Our Genesee neighborhood guide and Alaska Junction guide describe the streets around both of these areas. The buyer resources page explains how we approach comparing specific houses.
Is there still a light rail station planned near 35th Avenue SW and Genesee? No. The ST3 plan update adopted May 28, 2026 removed Avalon Station. The remaining West Seattle stations are Delridge and Alaska Junction.
When does construction start, and when do trains run? Sound Transit's milestone page lists construction from 2027 to 2035 and service in 2035, with major construction contracts expected to be awarded in 2027.
Where can I check whether a specific address is involved? Start with the two 2026 Board resolutions, R2026-18 from August and R2026-23 from October. The project team takes questions at [email protected].
If you are comparing Genesee houses and want to know how a particular block fits into the light rail timeline, from the cross streets near 41st and Alaska to the blocks that were planned around Avalon, Mara Haveson is glad to talk it through with you before you write an offer. Schedule a consultation when you're ready.